03Completion & handover

Works-As-Executed (WAE) Surveys

A works-as-executed survey shows what was actually built, with levels and positions compared to the approved design. Engineers and certifiers rely on it to sign off stormwater, OSD and civil works.

When you need it

Is this the survey you need?

  • Stormwater and OSD are finished and need engineer certification
  • The certifier or council asks for a WAE plan before the occupation certificate
  • Driveways, kerbs or other civil works need sign-off
  • A substation needs a WAE survey (on request)
  • An existing drainage system needs recording for future work

What's included

What we survey and show

  • Pits with surface and invert levels
  • Pipe sizes, grades and connections
  • OSD tank dimensions, levels, orifice and outlet details
  • Rainwater tanks and overflow connections where required
  • Driveway, kerb and footpath levels
  • Built levels shown against design levels on the plan
  • Easements shown where works sit inside them
  • Signed plan set out for the engineer's certification
  • Substation WAE when requested

Good to know

What the engineer needs

The engineer certifies that drainage and OSD were built to their design. To do that, they need measured levels: pit lids, inverts, pipe grades, tank floor and outlet levels. The WAE plan shows each measured value alongside the design value. Where something was built differently, the plan makes it clear, so the engineer can decide whether it still works or needs fixing. Ask your engineer for their preferred WAE format before we survey.

Survey before it's covered

Some parts of a stormwater system are hard to measure once they are buried, like pipe junctions or the inside of an OSD tank. Booking the WAE survey while pits are open and the tank is accessible saves digging later. If we set out the drainage originally, we already have the design levels and benchmark, which keeps the comparison simple and the records consistent.

How it works

From quote to signed plan

  1. CH 0.00

    Send the design

    Approved stormwater and civil drawings, and the engineer's WAE requirements.

  2. CH 25.00

    Survey the works

    Pits, pipes, tanks and surfaces are measured while they are accessible.

  3. CH 50.00

    Compare to design

    Built levels are compared with the design and differences noted.

  4. CH 75.00

    WAE plan

    You receive a signed WAE plan in PDF for the engineer.

What you get

Delivered to you

  • Signed WAE plan (PDF)
  • Design vs built levels

Checked and signed by Taha Abdo, Registered Surveyor SU010105.

Who it's for

We send the files to you, or straight to your architect, builder, engineer or certifier.

  • Builders
  • Developers
  • Certifiers & engineers

Questions

Common questions

When should I book the WAE survey?

When the drainage and OSD are complete but still accessible, with pit lids off and the tank open. Some engineers want parts surveyed before backfilling. Check with your engineer, and we will time the visit to suit.

Do you do substation WAE surveys?

Yes, when requested. The requirements come from the electricity network's own specification, so send us what they have asked for and we will confirm the scope and deliverables in the quote.

Is a WAE the same as a final survey?

No. The WAE covers drainage and civil works for the engineer. The final survey covers the building's location, setbacks and heights for the occupation certificate. Most projects need both, and they can often be done on the same visit.