The Two-Lot Subdivision Process in NSW
Splitting one lot into two follows a set path in NSW. Here is each step, who does what, and what drives the time and cost, from first check to new titles.
Step 1: Check the lot can be subdivided
Before anything is drawn, find out whether the planning rules allow two lots. Council's local environmental plan sets the zoning and minimum lot size, and the development control plan adds controls such as frontage, access and setbacks. A planning certificate from council shows the zoning and things like flood affectation.
Also check the title and the current deposited plan. Existing easements, restrictions and the shape of the lot can all affect where the new boundary can go. A town planner can give you a firm answer on the planning side. We can look at the title, the DP and the levels and tell you what the survey side involves.
Step 2: Detail and boundary survey
Your designer, planner and engineer need an accurate picture of the site. A detail and level survey shows existing buildings, levels and contours to AHD, trees, services and the neighbours' buildings. A boundary identification confirms where the boundaries actually are, rather than relying on fences or title dimensions.
This survey is the base for everything that follows, including the stormwater design and the proposed lot layout.
Step 3: Preliminary plan of subdivision
The preliminary plan shows the proposed lots, their dimensions and areas, and any new easements needed, for example for drainage or services. It goes in with the development application so council can assess the layout.
Where the subdivision is part of a dual occupancy or new house project, the lot layout is usually worked out together with the architectural design. Some subdivisions can be approved as complying development under the state Codes SEPP where the conditions are met. Your planner or certifier will confirm which path applies.
Step 4: Development consent and its conditions
Council, or the relevant planning panel, assesses the application and issues a consent with conditions. Read them carefully, because they drive the rest of the job. Conditions commonly cover:
- a Sydney Water compliance certificate
- electricity and other utility arrangements
- stormwater drainage, sometimes with a drainage easement over a neighbour
- driveways, kerb and footpath works
- easements and restrictions to be created on the title
Some conditions involve building works by other trades. The surveyor's part is the final plan, the marks on the ground and the easement documents.
Step 5: Final survey, plan and 88B instrument
Once the layout is fixed, we survey the land again for the final plan. The boundaries are defined from the evidence on the ground and in the surrounding plans, and the new corners are marked. Under the Surveyor-General's Directions, a subdivision of two or more lots must be connected to two permanent survey marks and given an accurate MGA orientation.
The final deposited plan is drafted to the Surveying and Spatial Information Regulation 2024 and the Registrar General's rules. If easements, restrictions or positive covenants are needed, they are set out in a section 88B instrument that is lodged with the plan.
Step 6: Subdivision certificate
Before the plan can be registered it needs a subdivision certificate, issued by council or by a registered certifier where that is allowed. The certifier checks that the consent conditions have been met. This is the step where outstanding conditions most often hold a job up, so it pays to work through them early.
Step 7: Lodgement and new titles
The plan, administration sheets and any 88B instrument are lodged online with NSW Land Registry Services through LRS Connect. LRS examines the plan and may issue a requisition asking for corrections. Once it is registered, new titles are created for each lot.
If a plan is lodged more than two years after the survey, the surveyor must also provide a certificate of currency confirming nothing relevant has changed on the ground.
Timing depends mostly on the consent conditions, utility approvals and council or certifier processing, rather than the survey itself. Cost depends on the site, the number of easements and how much boundary work is needed. We confirm both in a fixed-fee quote once we have seen the title, the DP and your plans.